Schedule
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Start
|
Finish
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Schedule
|
|
|
|
|
01-Jan-07
|
25-Feb-07
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ID
|
Task Name
|
Phase
|
% Complete
|
Duration (days)
|
Start
|
Finish
|
Predecessors
|
Assigned To
|
|
1
|
Initiation Phase (I)
|
I
|
100%
|
21
|
01-Jan-07
|
13-Jan-07
|
|
|
|
2
|
Prepare Project Proposal
|
I
|
100%
|
7
|
01-Jan-07
|
08-Jan-07
|
|
MT
|
|
3
|
Develop Project Charter
|
I
|
100%
|
2
|
01-Jan-07
|
03-Jan-07
|
|
MT
|
|
4
|
Project Charter Approval
|
I
|
100%
|
3
|
03-Jan-07
|
06-Jan-07
|
|
MT
|
|
5
|
Project Proposal Approval
|
I
|
100%
|
2
|
08-Jan-07
|
10-Jan-07
|
|
PC
|
|
6
|
Transfer Funding to Project
|
I
|
100%
|
3
|
10-Jan-07
|
13-Jan-07
|
5
|
PC
|
|
7
|
Prepare POs, Contracts
|
I
|
100%
|
4
|
01-Jan-07
|
05-Jan-07
|
|
MT
|
|
8
|
Initiation Phase Complete
|
I
|
100%
|
0
|
13-Jan-07
|
13-Jan-07
|
6
|
PC
|
|
9
|
Planning Phase (P)
|
P
|
100%
|
15
|
13-Jan-07
|
21-Jan-07
|
8
|
|
|
10
|
Develop Detailed Project Plan
|
P
|
100%
|
5
|
13-Jan-07
|
18-Jan-07
|
|
PC,MKT
|
|
11
|
Formation of Project Execution Team
|
P
|
100%
|
3
|
13-Jan-07
|
16-Jan-07
|
|
PC
|
|
12
|
Assign Marketing Resource
|
P
|
100%
|
2
|
18-Jan-07
|
20-Jan-07
|
10
|
MKT
|
|
13
|
Assign Human Resource
|
P
|
100%
|
3
|
18-Jan-07
|
21-Jan-07
|
10
|
HR
|
|
14
|
Assign Administrative Resource
|
P
|
100%
|
2
|
13-Jan-07
|
15-Jan-07
|
|
ET
|
|
15
|
Planning Phase Complete
|
P
|
0%
|
0
|
21-Jan-07
|
21-Jan-07
|
13
|
PC
|
|
16
|
Execution Phase (E)
|
E
|
0%
|
40.5
|
21-Jan-07
|
15-Feb-07
|
15
|
|
|
17
|
Kick-Off Meeting
|
E
|
0%
|
0.5
|
21-Jan-07
|
21-Jan-07
|
|
PC, AT, ET, HR
|
|
18
|
Purchase of Equipments
|
E
|
0%
|
15
|
21-Jan-07
|
05-Feb-07
|
|
AT, ET
|
|
19
|
Equipment installation
|
E
|
0%
|
10
|
21-Jan-07
|
31-Jan-07
|
|
AT, ET
|
|
20
|
End-User Training
|
E
|
0%
|
10
|
31-Jan-07
|
10-Feb-07
|
19
|
ET
|
|
21
|
Obtain User Acceptance
|
E
|
0%
|
5
|
10-Feb-07
|
15-Feb-07
|
20
|
HR
|
|
22
|
Execution Phase Complete
|
E
|
0%
|
0
|
15-Feb-07
|
15-Feb-07
|
21
|
PC
|
|
23
|
Closing Phase (C)
|
C
|
0%
|
12
|
15-Feb-07
|
25-Feb-07
|
22
|
|
|
24
|
Post-Execution Evaluation Meeting
|
C
|
0%
|
1
|
15-Feb-07
|
16-Feb-07
|
22
|
PC, MKT, AT, ET, HR, MT
|
|
25
|
Process Outstanding Invoices
|
C
|
0%
|
2
|
15-Feb-07
|
17-Feb-07
|
|
AT
|
|
26
|
Close POs, Contracts
|
C
|
0%
|
5
|
17-Feb-07
|
22-Feb-07
|
25
|
PC
|
|
27
|
Prepare Project Report
|
C
|
0%
|
1
|
22-Feb-07
|
23-Feb-07
|
26
|
PC
|
|
28
|
Transfer Accounting Documents to Accounting Department
|
C
|
0%
|
1
|
15-Feb-07
|
16-Feb-07
|
|
AT,ET
|
|
29
|
Project Report Approval
|
C
|
0%
|
1
|
23-Feb-07
|
24-Feb-07
|
29
|
MT, PC
|
|
30
|
Archive Project Documentations
|
C
|
0%
|
1
|
24-Feb-07
|
25-Feb-07
|
|
AT
|
|
31
|
Closing Phase Complete
|
C
|
0%
|
0
|
25-Feb-07
|
25-Feb-07
|
30
|
PC
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Abbreviations
|
|
|
|
|
|
|
|
|
|
MT
|
Management Team
|
|
|
|
|
|
|
|
|
PC
|
Project Charter
|
|
|
|
|
|
|
|
|
MKT
|
Marketing Team
|
|
|
|
|
|
|
|
|
HR
|
Human Resource Team
|
|
|
|
|
|
|
|
|
ET
|
Execution Team
|
|
|
|
|
|
|
|
|
AT
|
Administration Team
|
Gantt Chart
|
|
|
|
|
|
|
|
|
|
|
|
|
Start From
|
Finish To
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Gantt Chart
|
|
|
01-Jan-07
|
25-Feb-07
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ID
|
Task Name
|
Phase
|
Start
|
Finish
|
01-Jan-07
|
28-Jan-07
|
25-Feb-07
|
|
1
|
Initiation Phase (I)
|
I
|
01-Jan-07
|
13-Jan-07
|
|||||||||||||||
|
|
2
|
Prepare Project Proposal
|
I
|
01-Jan-07
|
08-Jan-07
|
|||||||||
|
|
3
|
Develop Project Charter
|
I
|
01-Jan-07
|
03-Jan-07
|
|||
|
|
4
|
Project Charter Approval
|
I
|
03-Jan-07
|
06-Jan-07
|
||||
|
|
5
|
Project Proposal Approval
|
I
|
08-Jan-07
|
10-Jan-07
|
|||
|
|
6
|
Transfer Funding to Project
|
I
|
10-Jan-07
|
13-Jan-07
|
||||
|
|
7
|
Prepare POs, Contracts
|
I
|
01-Jan-07
|
05-Jan-07
|
|||||
|
|
8
|
Initiation Phase Complete
|
I
|
13-Jan-07
|
13-Jan-07
|
|
|
|
9
|
Planning Phase (P)
|
P
|
13-Jan-07
|
21-Jan-07
|
||||||||||
|
|
10
|
Develop Detailed Project Plan
|
P
|
13-Jan-07
|
18-Jan-07
|
||||||
|
|
11
|
Formation of Project Execution Team
|
P
|
13-Jan-07
|
16-Jan-07
|
||||
|
|
12
|
Assign Marketing Resource
|
P
|
18-Jan-07
|
20-Jan-07
|
|||
|
|
13
|
Assign Human Resource
|
P
|
18-Jan-07
|
21-Jan-07
|
||||
|
|
14
|
Assign Administrative Resource
|
P
|
13-Jan-07
|
15-Jan-07
|
|||
|
|
15
|
Planning Phase Complete
|
P
|
21-Jan-07
|
21-Jan-07
|
|
|
|
16
|
Execution Phase (E)
|
E
|
21-Jan-07
|
15-Feb-07
|
||||||||||||||||||||||||||||||
|
|
17
|
Kick-Off Meeting
|
E
|
21-Jan-07
|
21-Jan-07
|
|
|
|
18
|
Purchase of Equipments
|
E
|
21-Jan-07
|
05-Feb-07
|
||||||||||||||||||
|
|
19
|
Equipment installation
|
E
|
21-Jan-07
|
31-Jan-07
|
||||||||||||
|
|
20
|
End-User Training
|
E
|
31-Jan-07
|
10-Feb-07
|
||||||||||||
|
|
21
|
Obtain User Acceptance
|
E
|
10-Feb-07
|
15-Feb-07
|
||||||
|
|
22
|
Execution Phase Complete
|
E
|
15-Feb-07
|
15-Feb-07
|
|
|
|
23
|
Closing Phase (C)
|
C
|
15-Feb-07
|
25-Feb-07
|
||||||||||||
|
|
24
|
Post-Execution Evaluation Meeting
|
C
|
15-Feb-07
|
16-Feb-07
|
||
|
|
25
|
Process Outstanding Invoices
|
C
|
15-Feb-07
|
17-Feb-07
|
|||
|
|
26
|
Close POs, Contracts
|
C
|
17-Feb-07
|
22-Feb-07
|
||||||
|
|
27
|
Prepare Project Report
|
C
|
22-Feb-07
|
23-Feb-07
|
||
|
|
28
|
Transfer Accounting Documents to Accounting Department
|
C
|
15-Feb-07
|
16-Feb-07
|
||
|
|
29
|
Project Report Approval
|
C
|
23-Feb-07
|
24-Feb-07
|
||
|
|
30
|
Archive Project Documentations
|
C
|
24-Feb-07
|
25-Feb-07
|
||
|
|
31
|
Closing Phase Complete
|
C
|
25-Feb-07
|
25-Feb-07
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|